Midland ISD Bond 2023

The bond was approved by 56.12% of voters participating in the election.

Lone Star Trails Ribbon Cutting

The Groundbreaking of LHS and MHS

Midland ISD Board approves John “Randy” Storie and Midland Middle Schools

May 21, 2025 

Midland ISD  announced the names and mascots for two new middle schools opening as part of the 2023 Bond Program: John “Randy” Storie Middle School and Midland Middle School. These names reflect deep community input and honor the rich history and legacy of education in Midland. Click here to read the official MISD press release.  

Goddard JHS and Midland Freshman Renovations

Goddard Junior High School - January 2026
Goddard Junior High School - January 2026
Goddard Junior High School - January 2026

Construction Update

Construction continues at the Goddard parking area and drop-off lane. Seventeen trees have been relocated from the Midland High School “tree farm” site to Goddard. The trees have been planted at their permanent location on the Goddard campus. Midland Freshman parking lot and drop-off lane construction continues.
Photo taken January 2026. 
 

Click here to learn more about the campus: Midland Freshman High School – Midland ISD Bond or Goddard Junior High School – Midland ISD Bond

Midland Freshman High School - January 2026

New Midland High School and Midland Lee High School

Construction Update

Construction at Midland High School is progressing right on schedule. Earthwork grading and dust mitigation continue throughout the site. Meanwhile, underground water, sewer, and electrical systems are being installed. Concrete block walls have started going up along with steel vertical construction, marking a significant milestone. The tree farm relocation has completed, allowing the Energy Transfer Pipelines to start the relocation process including significant earthwork/grading in those area and around the future athletic fields. Photo taken February 20, 2026. Click here to learn more about the campus:  Midland High School – Midland ISD Bond Profile

Construction Update

Midland Lee High School continues to run ahead of school. The road utility work under the Avalon and Thomason Road expansion has begun. Concrete block walls and steel structure continue going up throughout the building and steel structure continues going up throughout the academic wings.  Progress continues with the earthwork, concrete foundation, and utility crews working on site. Underground plumbing and electrical utilities are currently being installed throughout the building’s footprint to allow for the concrete slab installation to follow. Steel top-out is targeted for fall 2026, with permanent power and HVAC systems anticipated to come online in early 2027.  Photo taken February 06, 2026. Click here to learn more about the campus:  Midland Lee High School – Midland ISD Bond Profile

Project Timeline

Midland ISD has made a commitment to our community to stay on time and on budget with the bond projects, and we look forward to continuing to honor the 2023 bond timeframes, budgets, and projects that have been committed to voters.

Bond Packages Progress