The Midland ISD Bond Advisory Committee met for the ninth time to hear an update on the progress of the 2023 Midland ISD School Bond. The committee was reminded of their roles and responsibilities and heard reports on construction and project timelines and costs related to bond projects. |
|
PACKAGE 01 – LONE STAR TRAILS ELEMENTARY Lone Star Trails is nearing final completion as contractors wrap up remaining details. Door hardware has been received, and lock cores throughout the administration offices—including the final two between the reception area and hallway—were replaced last week. The Terrazzo floor, in the cafeteria/ commons, has also received its final polish. Additional interior updates include new tile along the front of the cafeteria serving line and installation of VCT flooring in the cafeteria office. All remaining work is taking place after hours and on weekends to avoid disrupting campus operations. Weekly coordination meetings with school administrators, maintenance staff, and Parkhill continue to address punch list items. Of the 659 items logged, roughly 92% are now complete. Concrete sidewalk replacement along the northwest corner of the school is scheduled for the Thanksgiving break to minimize impact on students and staff. The project remains in its one-year warranty period, with punch list resolution ongoing. Final Project Costs - Bond Budget: $53,300,000
- Projected Final Cost: $42,968,894
- Projected Savings: $10,331,106
|
|
PACKAGE 02 – NEW HIGH SCHOOLS New Midland Lee High School The project remains slightly ahead of schedule with steady progress across the expansive site. Crews continue grading, earthwork, and concrete footing pours, supported by ongoing dust mitigation. As crews advance deeper into the site, they will encounter more rock, slowing production and aligning progress more closely with Midland High School’s schedule. The next major milestone—vertical construction—is anticipated to begin in spring/summer 2026. Steel top-out is projected for fall 2026, with permanent power and HVAC systems coming online in early 2027. Off-Site Infrastructure (Avalon & Thomason Utilities – PKG 2A) - Approved at the October Board Meeting
- $401,213.73 below MISD budget
- $140,685.86 below City of Midland budget
|
|
New Midland High School The project is on schedule, with site activity increasing as conditions allow work to progress more efficiently than at Midland Lee. Crews continue earthwork, including soil lifting, boring, and pond excavation. Foundation and site preparations are advancing well. Coordination with Oncor remains ongoing to remove outdated electrical systems and install permanent power infrastructure. Midland High School is on track to align with Midland Lee in beginning vertical construction next year. Pipeline easement discussions are also underway. GMP Summary - Total GMP #1: $545,763,904
- Total GMP #2: $120,022,125
- Total GMP #3: $169,122,441
- Total Final GMP (PKG 02): $834,908,470
- Total Construction Budget: $841,400,000
- Total Savings: $6,491,530
|
|
PACKAGE 03 – ELEMENTARY SCHOOL RENOVATION – GROUP A Bond work across Emerson, Franks, Houston, Lamar, Long, Parker, South, and IDEA Travis Elementary Schools continues to progress. GMP #1 is complete, with final work at Emerson Elementary scheduled to wrap up in December as fire sprinklers are installed in the gym during the Christmas break. GMP #2 is slated for Board approval in January 2026. Preparations are underway for new security vestibule additions at Franks, Houston, and Lamar, which will begin early next year, while exterior maintenance and restroom renovations are planned across all campuses for summer 2026. At Emerson, the upcoming fire sprinkler installation marks the final GMP #1 task, with restroom renovations and exterior maintenance planned for next summer. Franks and Houston each continue preparing for their vestibule additions and summer renovation work, while IDEA Travis is moving forward with HVAC improvements in the IT room ahead of additional maintenance and restroom upgrades next summer. Parker is planning fire sprinkler work in the gym over Christmas Break, along with summer restroom and exterior updates. Sam Houston Collegiate Preparatory and Lamar are also preparing for their vestibule additions early next year, followed by restroom renovations, fire sprinkler installation (Lamar), and exterior maintenance in the summer. South and Jane Long Elementary Schools will complete bathroom remodeling, entry accessibility upgrades, fire sprinkler installation (Long), and exterior maintenance during the summer 2026 construction window. |
|
PACKAGE 04 – MIDDLE SCHOOL RENOVATION – GROUP A Construction at Goddard Middle School and Midland Freshman High School is moving forward as the construction contracts are currently under review by MISD. Contractor mobilization is expected to begin next week, with initial work focusing on the construction of new classrooms and a new administration area, which will require temporary entry locations. Future phases will include kitchen renovations and updates to existing classrooms. At both campuses, construction fencing and site preparation will soon be visible, and over the coming months, additions and expanded parking areas will take shape. The projects are on track for anticipated completion in December 2027. |
|
PACKAGE 05 – MIDDLE SCHOOL RENOVATION – GROUP B The design process is 100% complete. Construction at Alamo and Abell Junior High Schools is progressing on multiple fronts. The Multi-Purpose Building (MPB) is currently underway at both campuses, with grading and excavation in full swing north of the locker rooms at Alamo, and excavation soon to begin at Abell. Concrete foundations will be placed next, followed by steel framing, with both MPB projects targeting completion in early 2026. At Alamo Junior High, the contractor selection recommendation is scheduled for Board approval, with the first phase beginning in December 2025. This phase includes a new classroom addition and new library addition, while future phases will address kitchen renovations and updates to existing classrooms. The full Alamo project is anticipated to be completed by spring 2028. |
|
PACKAGE 08 – ELEMENTARY SCHOOL RENOVATIONS – GROUP B The design process is currently 50% complete. At Santa Rita Elementary, the drop-off drive, design development phase, and construction documents are 100% complete. Construction bids are planned for spring 2026, with work anticipated to begin in summer 2026. The project is expected to reach completion in fall 2028. |
|
PACKAGE 09 – MIDDLE SCHOOL RENOVATIONS – GROUP C The design phase for San Jacinto and Abell Middle Schools is currently 28% complete. Flooring upgrades were completed in summer 2025, and the schematic design phase is 100% complete. Construction documents are scheduled to be completed by summer 2026, with construction bids planned for late summer 2026 and work anticipated to begin in fall 2026. The project is expected to reach completion in fall 2028. |
PACKAGE 10 – ELEMENTARY SCHOOL RENOVATIONS – GROUP C The design phase is currently 28% complete. Construction documents are scheduled for completion by January 2026, with construction bids planned for spring 2026. Work is anticipated to begin in summer 2026, and the projects are expected to reach completion in fall 2028. |
PACKAGE 11 – ELEMENTARY SCHOOL RENOVATIONS – GROUP D The design phase is currently 11% complete. Construction documents are scheduled for completion by spring 2026, with construction bids planned for late spring 2026. Work is anticipated to begin in summer 2026, and the projects are expected to reach completion in December 2028. |
|
NEXT MEETING The next quarterly meeting of the Bond Advisory Committee will take place February 25, 2026. |
|
All students will graduate ready for college, career, or military. |
|
|
|
|