Bond Projects:

Scope of Work:

May 2025 Bond Update:

Package 02 -New Legacy High School

The design development is complete, and the Construction Documentation (CD) phase is 50% complete. The Avalon Drive and Thomason Drive design and coordination is in progress. Project cost estimates are in progress, and the district issued 50% CD for CMAR bidding on May 9. The interior selections and FFE were reviewed May 7-9. The groundbreaking ceremony will take place June 25 at 8:30 a.m. off Avalon Drive. The campus is scheduled to open in August of 2028.

Package 02 -New Midland High School

he design development is complete, and the Construction Documentation phase has begun and is 50% complete. The asbestos removal, building demolition, and tree salvage/relocation is complete. The design for the Wadley Avenue expansion is in progress. The district issued 50% CD for CMAR bidding on May 9. The interior selections and FFE were reviewed May 7-9. The groundbreaking ceremony will take place June 26 at 8:30 a.m. at 1600 E. Wadley Ave. The campus is scheduled to open in August of 2028.

2

Middle School Improvements

Scope of Work:

April 2025 Bond Update:

Package 04 -Middle School Reno Group A

Goddard Middle School

The relocation of portable buildings has been completed, and the Construction Documents have reached 100% completion. Spring 2025 Construction Documents are also finalized, with asbestos abatement contracted for summer 2025. The construction schedule is currently being finalized, with an estimated project completion date of May 2027.

Current Midland Freshman High School Building  – now named Midland Middle School

The Construction Document Phase has reached 100% completion, with additional documentation for spring 2025 also finalized. Asbestos abatement is scheduled to take place during the summer of 2025. The overall project is on track, with an estimated completion date of May 2027.

Package 05 -Middle School Reno Group B

The Construction Documents are currently 95% complete, with asbestos abatement scheduled for summer 2025. Portable building relocation is planned for the first week of summer. A recommendation regarding the Annex Buildings was presented this evening.

Package 09- Middle School Renovations Group C

San Jacinto Middle School and Abell Middle School are progressing with initial site surveys, STB submittal, and schematic design currently 25% complete. The design and construction schedule are in the process of being finalized. A bid recommendation for the Abell annex building portion of the project was presented tonight.

3

Safety & Security

April 2025 Bond Update:

Package 06 –

Safety

The project is currently in the closeout phase. All Texas Department of Licensing and Regulation (TDLR) inspections have been successfully passed. Camera installations and door access control systems have been completed along with the installation of new doors and secure vestibule storefronts featuring intruder-resistant film. Radio licenses have been obtained, and the central repeater tower has been completed. Final punch-list items are in progress and nearing completion.

4

Improvements to Aging Facilities

Southern District Solutions:

April 2025 Bond Update:

Package 08- Elementary School Renovations Group B

Santa Rita Elementary, Bush Elementary, Scharbauer Elementary, and De Zavala Elementary have completed scope-to-budget alignment and schematic design. The Design Development phase is currently 50% complete, and the construction schedule is being finalized. Drive and parking improvements at Santa Rita Elementary are already underway, with completion targeted for spring 2025. The School Board has approved the Schematic Design (STB), and the project remains well within budget.

Scope of Work:

April 2025 Bond Update:

Package 01 – Lone Star Trails Elementary

The construction of Lone Star Trails Elementary is 75% complete and remains on track to open in August 2025. Significant progress has been made with metal stud installation complete, roofing complete, and the drywall at 75% complete. All A/C units have been delivered and are 40% complete. Furniture is expected to be delivered on June 30. Additionally, the building plaque names have been verified and ordered, and staffing efforts are fully underway.